Project Construction Process Samples
This shows the cut out pocket for a small grotto at project start.  Pool steel is done and waterfall return line is stubbed up in back.
Waterfall return --- >
The Grotto steel has now been installed and is ready for Shotcrete/Gunite application.
The grotto is now finished and ready for the pool to be completed.
<--- Water level 
    approx. here.
Here we have a waterfall, pool and slide remodel add-on.  All steel has been installed and is ready for shotcrete/Gunite.
Shotcrete/Gunite is finished and feature has been waterproofed.
Project has been texture coated and painted and is ready for pool completion.
Project is done and pool has been finished and planted.
Shotcrete
hose.
Completed feature with water.